PREPARATION OF BAR BENDING SCHEDULE AND STEEL QUANTITY FOR ISOLATED FOOTING


PLAN AND CROSS SECTION FOR ISOLATED FOOTING


DETAILS FROM ABOVE DRAWING
  1.  Length of Footing -x 
  2.  Breadth of footing - y
  3.  Height of the footing -h (thickness)
  4.  Dia of the main reinforcement bars- dm
  5.  dia of distribution reinforcement bars- dd
  6.  The spacing of reinforcement bars- 
  7.   cover - c
BAR BENDING SCHEDULE AND STEEL QUANTITY FOR ISOLATED FOOTING
EXAMPLE 
         

DETAILS OBTAINED FROM EXAMPLE

  1.  Length of Footing -x =3m
  2.  Breadth of footing - y=2.1m
  3.  Height of the footing -h (thickness)=.35m
  4.  Dia of the main reinforcement bars- dm=16
  5.  dia of distribution reinforcement bars- dd=16
  6.  The spacing of reinforcement bars- .150mm
  7.   cover - c=50mm      
A. Calculation of number of main bars (main reinforcement)
Number of main bars =(X/Spacing of main reinforcement)+1
 =(3/.15)+1
=21 Nos
 Number of main bars =21*2= 42 nos (we have double mesh)
B. Calculation of number of distribution bars (distribution reinforcement)
Number of distribution bars =(y/Spacing of distribution reinforcement)+1 Number of distribution bars =(2.1/.15)+
 Number of distribution bars   =15 Nos
Number of distribution bars =15*2= 30 nos (we have double mesh)
C.cutting length of main bars (main reinforcement)
cutting length of main bars =(Y-2Cover)+2(h-2cover)-2(2dm) 
cutting length of main bars =(2.1-2*.05)+2(.35-2*.05)-2(2*16)
cutting length of main bars =2.436
 Total cutting length of main bars -2.436*42 =102.312
D.cutting length of Distribution bars (distribution reinforcement) 
A. cutting length of distribution bars =(X-2Cover)+2(h-2cover)-2(2dd)
cutting length of distribution bars =(3-2*.05)+2(.35-2*.05)-2(2*16)
 cutting length of distribution bars =3.336
 Total cutting length of distribution bars -3.336*30=100.08
E.STEEL QUANTITY CALCULATION
Weight = d2/162*total cutting length
  total weight of main bars =(16*16/162)*102.312 
  total weight of main bars =161.67 Kg
total weight of distribution bars =(16*16/162)*100.08
 total weight of distribution bars =158.15 Kg
BAR BENDING SCHEDULE FOR ISOLATED FOOTING