EARTHWORK EXCAVATION FOR BUILDINGS
SCOPE
This section consists of specifications pertaining
to all clearing, excavation and back filling necessary to carry out the
specified building works.
REFERENCE
All material, methods and workmanship shall
comply with the relevant British Standards and Codes of Practice. BS 6031 ; Code of Practice for Earthworks BS 8000 ; Code of Practice for Excavation and Filling
APPROVALS
The
Contractor shall submit method statement for excavation protection, dewatering
of excavations and back filling for the Engineer’s approval before commencement
of the work
POINTS CONSIDER BEFORE EXCAVATION
- Latest approved site layout drawing and architectural drawings available at site for the construction
- The Project Engineer shall check the Tender Drawing with the latest approved drawing if any variations notice to project manager
- should be checked for existing services
- If any existing services are available, trial holes will be dug by hand to expose the underground utilities and verify exact locations.
- Any services or any other observation which are suspected notice to project engineer.
- Adequate protection shall be provided to the existing services / structure as per the method approved by the Consulting Engineer, to ensure that no damages are imparted to them during the execution of work.1.
- A site survey shall be conducted to record existing ground level conditions, mark underground utility locations and excavation limits.
- A bench mark shall be established at site at some permanent, visible and undisturbed location, so as to enable the cross checking of levels at any time. The bench mark shall remain intact till the completion of the project
- The bench mark approved by Consulting Engineer
- work permit required for the execution
- Any vegetation, rubbish and other objectionable materials available on site shall be cleared and stored disposal area
- The marking shall be provided with suitable marking materials for clearly identifying the boundaries of the proposed facility
- Inspection request shall be forwarded to the Consulting Engineer for checking and approval
- Work shall commence at site only after the receipt of written approval on the inspection request submitted
- temporary road or working platform should provide better access for vehicle and equipments.
- EXECUTION
- Foundation pits shall be excavated according to the approved drawings and shall be of sufficient size to placing of footings/ground beams shown with full horizontal beds. Rounded or undercut corners and edges will not be permitted.
- Excavation shall be carried to the elevation shown on the drawings Excavation depths for foundations shall be only as directed by the Engineer. final depth as per soil investigation report
- All excavation material should be disposed outside the site as directed by the Engineer/Municipal authorities.
- the depth of excavation by mechanical means shall be limited to 20 cms higher than the required level. The last 20 cms shall be removed manually
- if presence of soft spots,sloping ground,slate,mud stone,if any other bring attention to consulting engineer and further excavation directed by the engineer
- SUPPORTING
- The Contractor shall be responsible at all times for carrying out excavation operations in a safe and prudent manner so that workmen and the public will be protected from unreasonable hazards at all times.
- Adequate vertical sheeting shall be used to protect employees, until completion of the work, to prevent damage to adjacent ground and structures..
- The sides of all excavations shall be adequately supported with planking, strutting or close sheeting as necessary to prevent slippage. and Edges of excavations must be kept clear for excavated material, vehicles and other loads.