BACK FILLING FOR STRUCTURAL EXCAVATION
GENERAL
Normally structural back filling allowed minimum 3 days after removed form work and curing
Back fill placed around the structure shall be same elevation and same time
Back fill shall be placed layer by layer even same moisture content
Without engineer approval no back fill placed
If any special back fill such as around pipe line and retaining wall not to disturbed levels and alignment
LAYING AND COMPACTION
GENERAL
Normally structural back filling allowed minimum 3 days after removed form work and curing
Back fill placed around the structure shall be same elevation and same time
Back fill shall be placed layer by layer even same moisture content
Without engineer approval no back fill placed
If any special back fill such as around pipe line and retaining wall not to disturbed levels and alignment
LAYING AND COMPACTION
Back fill placed layer not exceed 150 mm thick and proper compaction
The layer optimum moisture content tolerance ± 2%
Compacted soil with approved
compactors. Generally only plate
compactors and vibratory rollers will be allowed for back filling purposes
The compaction shall be done progressively from one side with each
succeeding pass uniformly overlapping the previous pass. The compaction shall continue until each
layer is compacted to the degree specified.
Any area
inaccessible to normal compaction equipment shall be compacted by means of
mechanical tampers until satisfactory compaction is achieved.
COMPACTION REQUIREMENTS
The following degree of compaction shall be obtained:
Fills under building foundations, soil rafts
|
97%
|
modified proctor
|
Structural back fill
|
95%
|
standard proctor
|
Fill under ground slabs
|
97%
|
standard proctor
|
Fill under asphalt and paving top layer 250mm
|
97%
|
standard proctor
|
Fill under asphalt and paving lower layers
|
95%
|
standard proctor
|
Non-structural back fill for making up levels in
landscaped areas
|
85%
|
standard proctor
|